Requested Application Details

Application type:

or
or

Verify your email

We sent a verification code to

Didn't receive the code? Resend

Complete your profile

Email verified. Complete your profile.

CEB SOLAR PHOTOVOLTAIC (PV) SCHEME (HOUSEHOLDS)

APPLICATION FORM
FOR RENEWABLE ENERGY (RE) OF CAPACITY UP TO 10 kW

Instructions for application

Fetch my CEB billing information

Completing Registration

 

0%
MSDG Version 3.0 — September 2024

Grid Code — Medium Scale Distributed Generation (MSDG)

22 kV Distribution Network · Above 50 kW and not exceeding 500 kW

Foreword

This document aims to help the public better understand the application procedure, the requirements of the MSDG Grid Code and other issues relating to the Medium Scale Distributed Generation project. Compliance with this Grid Code is mandatory for any prospective applicant. The provisions of the Electricity Act 2005 and the Environment Protection Act 2002 shall also be complied with.

Disclaimer

The MSDG Grid Code constitutes the minimum technical requirements for the connection of medium-scale distributed generation to the CEB distribution network.

The applicable capacity is above 50 kW and not exceeding 500 kW at the point of delivery, unless otherwise revised by the CEB.

The DC/AC ratio shall not exceed 1.2. The CEB reserves the right to revise this Grid Code at any time.

Revision history

Version Date Amendments
Version 1.0 May 2016 Initial version
Version 2.0 December 2017 Updates to protection settings and standards
Version 2.1 October 2019 Updates to interconnection and metering requirements
Version 3.0 September 2024 Applicable capacity, DC/AC ratio and Installation Certificate

Chapter 1 — Purpose of the Grid Code

This Grid Code describes the technical criteria and requirements for connecting distributed generation units with a capacity above 50 kW but not exceeding 500 kW to the CEB 22 kV distribution network. It covers PV, wind, hydro and biomass technologies.

More details on the schemes are available on the CEB website at ceb.mu/projects/energy-schemes.

Chapter 2 — Connection process

  1. 1 Submission of the MSDG application form and technical specifications to the CEB MSDG Unit, Curepipe.
  2. 2 Assessment of the proposal against Grid Code requirements. A system impact study may be required.
  3. 3 Issue of a Letter of Intent with the allocated capacity and applicable fees.
  4. 4 Acceptance of the conditions and payment of the fees by the applicant.
  5. 5 Signing of the Connection Agreement during a joint site meeting.
  6. 6 Completion of the interconnection works during a planned supply outage.
  7. 7 Completion of the MSDG installation within 12 months. Submission of the Installation Certificate.
  8. 8 Testing and commissioning by the CEB.

Chapter 3 — Technical requirements of the Grid Code

1. Design parameters

All MSDG installations shall have a three-phase output only. All inverters shall be of the Grid Forming type. The DC/AC ratio shall not exceed 1.2.

Table 1 — Normal operating parameters
Description Range
Statutory voltage range 230/400 V ± 6 %
Short-circuit level (excluding MSDG contribution) 18 kA (50 Hz, 1 sec)
Nominal frequency 50 Hz
Statutory frequency deviation 50 Hz ± 1.5 %
Operating frequency range 47 Hz – 52 Hz

2. Protection requirements

The DG shall be protected against: overload, short-circuit, earth faults, overcurrent, abnormal voltages, abnormal frequencies, lightning, and loss of mains.

Table 2 — Default interface protection settings
Parameter Symbol Trip setting Clearing time
Overvoltage (a) U>> 230 V + 10 % 0.2 s
Overvoltage U> 230 V + 6 % 1.5 s
Undervoltage U< 230 V − 6 % 1.5 s
Overfrequency (b) f> 50 Hz + 1.5 % 0.2 s
Underfrequency f< 50 Hz − 6 % 0.5 s
Loss of mains df/dt & Vector Shift 2.5 Hz/s & 10° 0.5 s

Islanding: The DG shall disconnect within 0.2 seconds of the formation of an island. Following disconnection, the DG shall remain disconnected until the voltage and frequency have remained within nominal limits for at least 3 minutes.

WARNING: "CONDUCTORS MAY REMAIN LIVE WHEN THE ISOLATOR IS OPEN" shall be displayed prominently at the installation.

3. Power quality

3.1 DC injection: The DG shall not inject direct current exceeding 0.25 % of the rated AC output current per phase.

3.2 Flicker: The installation shall not cause abnormal flicker beyond the limits of the "Maximum Irritation Threshold Curve" according to IEEE 519-2014.

3.3 Harmonics: Voltage THD shall not exceed 5.0 % of the fundamental measured at the PCC.

Table 3 — Current harmonic distortion limits (IEEE 519-2014)
Odd harmonics Max distortion
3rd – 9th 4.0 %
11th – 15th 2.0 %
17th – 21st 1.5 %
23rd – 33rd 0.6 %
Above the 33rd 0.3 %

3.5 Unbalance: The total voltage unbalance in the network shall be less than 2 %. The contribution of an installation shall not cause an increase in unbalance of more than 1.3 %.

3.6 Step voltage variation: Variations caused by connection/disconnection shall not exceed ±3 % for planned events and ±6 % for unplanned outages.

Table 4 — Maximum inrush current
Connection Inrush current
LV three-phase 30 A
MV (via transformer) As per CEB study

4. Power factor

The power factor of the DG under normal conditions shall be between 0.95 leading and 0.95 lagging over the full statutory nominal voltage range.

5. Network maintenance

Preventive and corrective maintenance of the feeder to which the DG is connected may interrupt production. No compensation shall be applicable for loss of production due to planned or emergency maintenance.

6. Safety, isolation and switching

6.1 Isolation: The system shall be isolated from all possible sources of supply. A switch with visible contact that can be locked in the open position shall be installed.

6.2 Installer: The installer shall hold an MQA-approved or equivalent qualification in electrical installation and renewable energy systems acceptable to the CEB.

6.3 Registered Professional Engineer: A Registered Professional Engineer shall sign the Installation Certificate and supervise the interconnection works.

7. Metering

A bidirectional Import/Export meter of class 0.5 or better shall be installed at the Supply Terminal. A second meter measuring the gross production of the MSDG shall also be installed.

The MSDG promoter shall obtain CEB approval before ordering CTs and VTs, and shall send them to the CEB Metering Laboratory Section for testing prior to installation.

8. Standards and regulations

All equipment shall comply with the following standards (latest applicable editions):

PV modules

Standard Description
IEC 61215 Terrestrial PV modules — Design qualification and type approval
IEC 61701 Salt mist corrosion testing of PV modules
IEC 61730 PV module safety qualification

PV inverters

Standard Description
IEC 62109-1/2 Safety of power converters for use in photovoltaic power systems
IEC 62116 Anti-islanding prevention for utility-interconnected PV inverters
IEC 61683 Procedure for measuring efficiency

Grid connection

Standard Description
IEC 61727 Photovoltaic (PV) systems — Characteristics of the utility interface
IEC 62271 High-voltage switchgear and controlgear
IEC 60076 Power transformers

General standards

Standard Description
IEC 60364-5-54 Earthing arrangements and protective conductors
IEC 62305-3 Protection against lightning
IEEE 519 Control of harmonics in electrical power systems

Chapter 4 — Amendments to the Grid Code

  • Some values need to be revised owing to system evolution.
  • The quantity of generation in one or more segments requires stricter control.
  • Better alignment with operating conditions is required.
  • Additional amendments to the Grid Code shall be prepared as an addendum.

Chapter 5 — Non-compliance with the Grid Code

In case of non-compliance, the CEB will inform the owner in writing of the deviations found. The owner shall have 30 days to rectify the deviations.

Failing that, the CEB shall be entitled to disconnect the DG. Reconnection will require certification of compliance by the CEB.

The CEB shall be entitled to disconnect the DG without prior notice if the installation conditions are dangerous.

Annex 1 — Abbreviations and definitions

AC Alternating Current
CEB Central Electricity Board
DC Direct Current
DG Distributed Generation
Grid Forming Inverter capable of forming and maintaining network voltage and frequency
HV High Voltage — systems > 1000 V AC or 1500 V DC
Islanding Condition in which part of the CEB network is supplied by a DG while electrically separated from the rest of the system
MSDG Medium Scale Distributed Generation — above 50 kW and not exceeding 500 kW
MQA Mauritius Qualifications Authority
PCC Point of Common Coupling — connection point to the CEB network
PV Photovoltaic
DC/AC Ratio Ratio between the DC peak power of the modules and the nominal AC power of the inverter (max 1.2)
CT Current Transformer
THD Total Harmonic Distortion
VT Voltage Transformer

Annex 2 — Installation certificate

The applicant/installer shall submit a duly signed certificate on company letterhead with company stamp to the CEB. The Installation Certificate shall confirm:

  • Installed capacity [kW] and site address
  • Equipment details: PV modules and inverters (brand, model, rating, quantity, serial numbers)
  • DC/AC ratio of the installation
  • Inverter protection parameters: voltages, frequencies, loss of mains and reconnection time
  • Name and signature of the Registered Professional Engineer with registration number
  • Stamp of the installing company and date

Annex 3 — Commercial commissioning

Commercial commissioning of the MSDG shall be subject to the signature of the Connection Agreement by all parties and verification of the installation's compliance with this Grid Code by CEB representatives.

Ready to submit your MSDG application?

Use our online assistant to complete your CEB form step by step.

Start my application