Requested Application Details

Application type:

or
or

Verify your email

We sent a verification code to

Didn't receive the code? Resend

Complete your profile

Email verified. Complete your profile.

CEB SOLAR PHOTOVOLTAIC (PV) SCHEME (HOUSEHOLDS)

APPLICATION FORM
FOR RENEWABLE ENERGY (RE) OF CAPACITY UP TO 10 kW

Instructions for application

Fetch my CEB billing information

Completing Registration

 

0%
SSDG Version 3.0 — April 2026

Grid Code — CEB Solar Photovoltaic Scheme (Households)

Small Scale Distributed Generation · Low Voltage 230/400 V Network · ≤ 50 kW AC

Foreword

This document aims to help the public better understand the application procedure, the requirements of the Grid Code and other issues relating to the Small Scale Distributed Generation (SSDG) project. Any applicant wishing to benefit from the SSDG scheme is informed that:

  • Compliance with this Grid Code is mandatory.
  • The provisions of the Electricity Act shall be complied with.
  • This Grid Code will be revised and updated as required.

Disclaimer

The "Grid Code for Small Scale Distributed Generators (SSDG)" of the CEB constitutes the minimum technical requirements for the connection of distributed generation (DG), with or without a battery energy storage system (BESS), to the CEB low-voltage distribution network.

Injection of active power from the DG shall in no case exceed 50 kW AC at the point of delivery, as measured by the CEB Import/Export meter, or the maximum capacity of the scheme applicable at that time.

The CEB reserves the right to revise this Grid Code at any time.

Revision history

Version Date Amendments
Version 2.3 September 2019 Minor revisions
Version 3.0 April 2026 Integration of requirements for SSDG with Battery Energy Storage System (BESS)

Chapter 1 — Purpose of the Grid Code

The Grid Code describes the technical criteria and requirements for connecting Small Scale Distributed Generators (SSDG) to the CEB low-voltage network (230/400 V). It covers electricity generation and storage from inverter-based renewable energy sources such as photovoltaic.

More details on the schemes are available on the CEB website at ceb.mu/projects/energy-schemes.

Chapter 2 — Grid Code requirements and safety aspects

1. Design parameters

All DGs with an export capacity below 5 kW AC may have either single-phase or three-phase output. All DGs with an export capacity of 5 kW AC and above shall have three-phase output only. All inverters shall be of the Grid Forming type.

Table 1 — Normal operating parameters of the CEB LV network
Description Plage
Voltage 230/400 V ± 6 %
Short-circuit characteristics (1 sec) 18 kA, (50 Hz)
Nominal frequency 50 Hz
Legal frequency deviation 50 Hz ± 1,5 %
Operating frequency range 47 Hz – 52 Hz

The CEB LV network is designed as a TT system. These values are mandatory for all DGs, with or without BESS.

2. Protection requirements

The DG shall be protected against: overload, short-circuit, earth faults, overcurrent, abnormal voltages, abnormal frequencies, lightning, and loss of mains.

2.4 Default trip settings

Table 2 — Default interface protection settings
Parameter Symbol Trip setting Clearing time
Overvoltage (a) U>> 230 V + 10 % 0,2 s
Overvoltage U> 230 V + 6 % 1,5 s
Undervoltage U< 230 V − 6 % 1,5 s
Overfrequency (b) f> 50 Hz + 1,5 % 0,2 s
Underfrequency f< 50 Hz − 6 % 0,5 s
Loss of mains df/dt & Vector Shift 2,5 Hz/s & 10° 0,5 s

(a) If the DG can generate a voltage higher than the U>> setting, stage 2 overvoltage is required. (b) The f> setting is lower than the maximum frequency in Table 1 to avoid the DG contributing to frequency rise.

2.5 Network islanding

DG without BESS: The DG shall not energize the CEB network during outages. It shall disconnect within 0.2 seconds of the formation of an island.

DG with BESS: A DG with BESS may operate in island mode. If it exports energy in grid-connected mode, it shall disconnect within 0.2 seconds of the formation of an island.

2.6 Reconnection

Following disconnection, the DG shall remain disconnected until the voltage and frequency have remained within nominal limits for at least 3 minutes. Automatic reconnection is only permitted when the disconnection is due to parameters outside the normal range in Table 1.

2.8 Earthing

Earthing shall comply with IEC 60364-5-55. The TT earthing system is standard on the CEB network. Neutral and earth conductors shall be separated throughout the installation.

WARNING: "CONDUCTORS MAY REMAIN LIVE WHEN THE ISOLATOR IS OPEN" shall be displayed prominently at the installation.

3. Power quality

3.1 DC injection: The DG shall not inject direct current exceeding 0.25 % of the rated AC output current per phase.

3.2 Flicker: The installation shall not cause abnormal flicker beyond the limits of the "Maximum Irritation Threshold Curve" according to IEEE 519-2014.

3.3 Harmonics: Voltage THD shall not exceed 5.0 % of the fundamental at 400 V measured at the PCC.

Table 3 — Current harmonic distortion limits (IEEE 519-2014)
Odd harmonics Max distortion
3rd – 9th 4,0 %
11th – 15th 2,0 %
17th – 21st 1,5 %
23rd – 33rd 0,6 %
Above the 33rd 0,3 %

3.4 Overvoltages: Resistance to oscillatory and fast transient overvoltages shall comply with IEC 62305-3 at test levels of 1.5 kV.

3.5 Unbalance: The total voltage unbalance in the network shall be less than 2 %. The contribution of an installation shall not cause an increase in unbalance of more than 1.3 %.

3.6 Step voltage variation: Variations caused by connection/disconnection shall not exceed ±3 % for planned events and ±6 % for unplanned outages.

Table 4 — Maximum inrush current
Connection Inrush current
Single-phase 19 A
Three-phase 30 A

4. Power factor

The power factor of the DG under normal conditions shall be between 0.95 leading and 0.95 lagging over the full legal nominal voltage range.

5. Network maintenance

Preventive and corrective maintenance on the feeder to which the DG is connected may interrupt production. No compensation shall be applicable for production loss due to maintenance.

6. Safety, isolation and switching

6.1 Rules for working on the LV network

  • The system shall be isolated from all possible sources of supply; all switches shall be locked in visibly open positions.
  • The DG shall have a local means of isolation that disconnects all live conductors, including the neutral.
  • A switch with a visible break that can be locked in the open position shall be installed to disable automatic or manual closing of the interconnection switch.
  • CEB shall maintain an updated register of all DG units, including precise addresses, connection points and the associated transformers.

6.2 Safety concerns

  • People shall be warned that the installation includes a DG so that safety precautions are taken to avoid the risk of electric shock.
  • PV cells generate energy when exposed to light. Additional precautions such as covering the PV cells are required before any intervention.
  • The DG manufacturer or supplier shall certify compliance with the Electrical Equipment Safety Regulations and the Electromagnetic Compatibility Regulations.

6.3 Electrical installer

The installer shall affix a label indicating the next scheduled maintenance and inform CEB so that the SSDG register can be updated. The installer shall be qualified in the field of SSDG installations and hold an MQA-approved qualification or equivalent in electrical installation and renewable energy installations acceptable to CEB.

7. Metering

A bidirectional Import/Export meter measuring both imported and exported energy shall be installed at the Supply Terminal. A second meter measuring the gross production of the SSDG shall also be installed.

The SSDG promoter shall obtain CEB approval before ordering CTs and VTs, and shall send them to the CEB Metering Laboratory Section for testing before installation.

8. Standards and regulations

All electrical apparatus, materials and wiring shall comply with the Electricity Act, the CEB Act, the Electricity Regulations, this Code and the following standards in their latest applicable editions:

Modules PV

Standard Description
IEC TS 62804-1/-2 Test methods for the detection of voltage-induced degradation
IEC 61215 Crystalline silicon terrestrial PV modules — Design qualification and type approval
IEC 61701 Salt mist corrosion testing of PV modules
IEC 61730 PV module safety qualification

PV inverters

Standard Description
IEC 61683 Power conditioners — Procedure for measuring efficiency
IEC 62109-1/2 Safety of power converters for use in PV power systems
IEC 62116 Test procedure for prevention of islanding for grid-connected PV inverters

Grid-connected PV systems

Standard Description
IEC 61727 PV systems — Characteristics of the utility interface
EN 50438 Requirements for the connection of micro-generators in parallel with public low-voltage distribution networks
IEC 62446-1 PV systems — Requirements for testing, documentation and maintenance
IEC 61724 PV system performance monitoring

General engineering standards

Standard Description
IEC 60364-5-55 Electrical installations of buildings
IEC 62305-3 Protection against lightning — Physical damage and danger to life
IEC 60364-5-54 Earthing arrangements and protective conductors
IEEE C37.90 IEEE standard for relays and relay systems

Power quality

Standard Description
IEC 61000-3-2 Limits for harmonic current emissions
IEC 61000-3-3 Limitation of voltage changes, voltage fluctuations and flicker
IEEE 519 Recommended practice for harmonic control in electric power systems

Battery Energy Storage System (BESS)

Standard Description
IEC 62933 Series of standards for electrical energy storage systems (ESS)
IEC 62619 Safety requirements for secondary lithium cells and batteries for industrial applications
IEC 63056 Safety requirements for secondary lithium cells and batteries for use in electrical energy storage systems
UL 1973 / UL 9540 Certification standards for battery safety testing
IEC 61000 series Electromagnetic compatibility (EMC)

Chapter 3 — Grid Code amendments

CEB shall propose a new version of this Grid Code in the following cases:

  • Certain values need to be revised due to system evolution.
  • The amount of generation in one or more segments requires stricter control.
  • Better alignment with operating conditions is required.
  • Additional amendments to the Grid Code must be prepared as an addendum.

Chapter 4 — Non-compliance with the Grid Code

In the event of non-compliance with any technical provision of this Grid Code, CEB shall notify the owner in writing of the deviations observed. The DG owner shall have 30 days to rectify the deviations.

Failing this, CEB shall be entitled to disconnect the DG.

CEB shall be entitled to disconnect the DG without prior notice if the installation conditions are dangerous or create unavoidable safety risks.

Reconnection shall require CEB to certify that the installation complies with this Grid Code. Applicable fees shall be the same as standard reconnection fees.

Annex 1 — Abbreviations and definitions

AC Alternating Current
Applicant Electricity producer through an SSDG installation
BESS Battery Energy Storage System
CEB Central Electricity Board
DC Direct Current
DG Distributed Generation
Flicker Voltage variation sufficient to allow visual observation of a change in the intensity of an electric light source
Grid Forming Type of inverter capable of forming and maintaining grid voltage and frequency
HT High Voltage — systems normally operating above 1000 V AC or 1500 V DC
Islanding Condition in which a part of the CEB network is energized by one or more SSDGs via their PCC(s) while electrically separated from the rest of the system
kV Kilovolt
kW Kilowatt (1 000 W)
kWh Kilowattheure
LV Low Voltage — systems normally operating at not more than 1000 V AC or 1500 V DC
MQA Mauritius Qualifications Authority
PCC Point of Common Coupling — point at which an SSDG is connected to the CEB network
PV Photovoltaic
RE Renewable Energy
SSDG Small Scale Distributed Generation
THD Total Harmonic Distortion
TT system TT earthing system — the consumer's protective earthing connection is provided by a local earth connection

Annex 2 — Installation Certificate

The applicant/installer shall submit a duly signed certificate on company letterhead bearing the company stamp to CEB. The Installation Certificate shall confirm:

  • Installed capacity [kW] and site address
  • Details of installed equipment: PV Modules and Inverter (make, model, rated power, quantity, serial numbers)
  • Inverter protection settings: Overvoltage ×2, Undervoltage, Overfrequency, Underfrequency, Loss of mains df/dt & Vector shift, Reconnection time, Active power limit
  • Line impedance (ohm)
  • Name and signature of the installing company and the Registered Professional Engineer / Installer (with RPEM number where applicable)
  • Name and signature of the Applicant
  • Company stamp and date

Annex 3 — Commercial commissioning

Commercial commissioning of the SSDG is subject to the Connection Agreement being signed by all parties and to verification by CEB representatives that the installation complies with this Grid Code. The installation shall be commissioned after signature of the Connection Agreement.

Ready to submit your SSDG application?

Use our online assistant to complete your CEB form step by step.

Start my application